Neighbors invited to Nov. 2 meeting on a quiet zone to stop train horns at four downtown crossings

The city has scheduled a 6 p.m. neighborhood meeting at the library on its railroad quiet zone, which could end routine horn blasts at Santa Rita Road, St. Mary Street, Rose Avenue and Angela Street.

Reese Hardy· AI-assisted, edited by Jake Team

October 20, 20262 min read

Pleasanton City Hall - illustration, Jake Team LLC

Residents who live with train horns sounding through downtown at all hours will get a chance to weigh in on the city's plan to silence them.

Pleasanton has scheduled a Railroad Quiet Zone Neighborhood Meeting for Monday, Nov. 2, at 6 p.m. at the Pleasanton Library, 400 Old Bernal Ave., according to the city's public meetings calendar. The listing was posted Oct. 14; no agenda or presentation had been attached as of Tuesday.

What a quiet zone does

Federal rules make engineers blow the horn four or more times, at 96 decibels or louder, before every public crossing. A quiet zone lifts that requirement once crossings get extra safety features, such as raised median islands that keep drivers from weaving around lowered gates.

Pleasanton's zone would take in the city's four public crossings on the Union Pacific line: Santa Rita Road, St. Mary Street, Rose Avenue and Angela Street. The tracks carry both freight and ACE (Altamont Corridor Express) commuter service through Niles Canyon and Sunol, across downtown and along Stanley Boulevard toward Livermore.

Sunol set up its own quiet zone in 2018, and Pleasanton's plan follows that model.

Where the project stands

The council approved a capital project in August 2025 to study and design the zone, partly in response to complaints from residents. On Dec. 16, 2025, it unanimously hired Kimley-Horn and Associates, the only firm to bid, under a contract capped at $168,858. The money came from surplus funds left over from the Bernal synthetic turf replacement project, The Independent reported at the time.

Kimley-Horn's proposal laid out a 21-month schedule that moves from early analysis and concepts to outreach, a review by the council, and then final plans and permits.

Cost estimates have dropped since the idea first came up. A 2007 staff review put crossing upgrades with motorized gates at about $2 million; the city now expects medians or comparable designs costing roughly a tenth of that. If the consultant finds more is needed, the project would need more money and another council approval.

As of last December, the city's best-case estimate had construction running from January to September 2027, depending on how quickly Union Pacific, ACE and the Federal Railroad Administration sign off.

Resident Jim Lehrman, who helped draw attention to the noise, told The Independent at the time that the work would take "the better part of two years" and need railroad and federal approvals, but that he expected it to improve life downtown.

Sources

pleasantonca.api.civicclerk.com

independentnews.com

cityofpleasantonca.gov

Share

Reese Hardy· AI-assisted, edited by Jake Team

Reese Hardy writes about community life, schools, public safety, and local events in Pleasanton.

Related Stories

More in California