Unfinished capital projects would carry $92.6 million into this year, with storm drains flagged as a strain

A year-end capital report up Tuesday says the storm drain capital fund leans heavily on the general fund, while Sycamore Creek drainage work is set to start in March 2027.

Reese Hardy· AI-assisted, edited by Jake Team

November 29, 20262 min read

Civic finance and infrastructure - illustration, Jake Team LLC

Pleasanton's unfinished capital projects would carry $92.6 million forward from last fiscal year under a year-end report the City Council takes up Tuesday, Dec. 1.

The report, from Financial Services Manager Chris Yi, Finance Director Susan Hsieh and Public Works Director Siew-Chin Yeong, covers the Capital Improvement Program as of June 30, 2026. The figures are unaudited; the audited numbers are due in the city's annual financial report in January.

Of the money being carried forward, about $68.1 million is restricted, meaning it can only go to set purposes such as park and facility impact fees, water, sewer and golf course funds, and transportation money. The other $24.5 million, mostly from the general fund, is flexible and is used largely for streets, parks and storm drains.

Staff says $72.9 million of the total is tied to active projects, while $19.7 million sits in reserves.

Storm drains lean on the general fund

The report singles out the storm drain capital fund, which it says depends heavily on general fund support, as the storm drain operating fund does. Staff calls that approach unsustainable and says options will come back to the council later.

On the storm drain list, design and environmental permitting moved ahead on Sycamore Creek improvements meant to add capacity and cut localized flooding, with construction expected to start in March 2027. The city is still working with FEMA and regulators on permanent repairs from the 2023 winter storms at the East Vineyard detention pond, Oak Tree Farm, the Augustin Bernal Trail and Park Parkway.

Other results

  • The city had 11 projects in planning, 24 in design and 21 under construction last year, and finished 25.
  • It recorded no sanitary sewer overflows in the fiscal year.
  • A $1 million state grant paid for a feasibility study on a new groundwater well, and the city worked with the EPA to shift an earlier $2 million grant to designing the well.
  • One project went over budget: the West Las Positas Boulevard multimodal rebuild, by $5,232, after the city used the last of its Measure B bike and pedestrian money before that funding expired. The council is asked to amend the budget to match.

The meeting starts at 7 p.m. in the City Council Chamber, 200 Old Bernal Ave., and can also be joined on Zoom.

Sources

pleasantonca.api.civicclerk.com

pleasantonca.api.civicclerk.com

Share

Reese Hardy· AI-assisted, edited by Jake Team

Reese Hardy writes about community life, schools, public safety, and local events in Pleasanton.

Related Stories

More in California