Pleasanton's unfinished capital projects would carry $92.6 million forward from last fiscal year under a year-end report the City Council takes up Tuesday, Dec. 1.
The report, from Financial Services Manager Chris Yi, Finance Director Susan Hsieh and Public Works Director Siew-Chin Yeong, covers the Capital Improvement Program as of June 30, 2026. The figures are unaudited; the audited numbers are due in the city's annual financial report in January.
Of the money being carried forward, about $68.1 million is restricted, meaning it can only go to set purposes such as park and facility impact fees, water, sewer and golf course funds, and transportation money. The other $24.5 million, mostly from the general fund, is flexible and is used largely for streets, parks and storm drains.
Staff says $72.9 million of the total is tied to active projects, while $19.7 million sits in reserves.
Storm drains lean on the general fund
The report singles out the storm drain capital fund, which it says depends heavily on general fund support, as the storm drain operating fund does. Staff calls that approach unsustainable and says options will come back to the council later.
On the storm drain list, design and environmental permitting moved ahead on Sycamore Creek improvements meant to add capacity and cut localized flooding, with construction expected to start in March 2027. The city is still working with FEMA and regulators on permanent repairs from the 2023 winter storms at the East Vineyard detention pond, Oak Tree Farm, the Augustin Bernal Trail and Park Parkway.