Project Overview and Previous Approval
The Pleasanton City Council previously approved the Arroyo Lago subdivision during a July 27, 2026 meeting. That approval included annexation proceedings, General Plan Amendments, rezoning, a Planned Unit Development plan, and a Vesting Tentative Subdivision Map.
The initial conditions of approval did not include specific requirements for wastewater treatment facility analysis or funding.
New Wastewater Conditions
The Dublin San Ramon Service District submitted a comment letter requesting two additional conditions related to the project. Staff members have concurred with the district that these additions would clarify developer obligations for necessary studies and fair share improvement costs.
The revised ordinance will formally add these requirements as Conditions of Approval 134 and 135.